SBD-62 CAPM
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/02/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
It is proposed to cold-in-place recycle (CIR), overlay existing asphalt pavement, provide pavement tapered edges along State Route 62 (SR-62) from PM 94.0 to PM 106.0 and reconstruct slope embankments at two locations at approximately PM 95.7 and PM 101.8 in San Bernardino County. All work will remain within the limits of the existing right-of-way, except for two TCEs near Post Miles 95.7 and 101.8 where streambed access is needed for installation of RSP. Work involves federal land (BLM [Bureau of Land Management] Needles jurisdiction).
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|