San Joaquin Bridge Maintenance

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Class of Action Changed

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CLASS OF ACTION CHANGED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

California

LEAD AGENCY
California

Description:

During the course of project development, it was determined that the following project could be down scoped and qualify as a categorical exclusion (CE). A CE was finalized on 7/18/2018 and the project is considered complete.

CEs are not required to be tracked on the Dashboard.

 

Bridge preventative maintenance: The project proposes to replace the wiring (submarine cable, power, and controls), traveling cables, conduts, junction boxes, motor control cabinet, and bridge operation control console to accommodate new equipment and comply with current codes and regulations. The existing bridge is located on Cal 4, on the County line of San Joaquin and Contra Costa Counties.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete