SAC-5 Corridor Improvement Project
PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-3/d3-projects/d3-i5-corridor-impro…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/01/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans) proposes to construct improvements consisting of managed lanes in each direction, auxiliary lanes, and Intelligent Transportation (ITS) in Sacramento County on Interstate 5 (I-5) from south of the I-5 and SR-50 interchange to the Sacramento River Bridge (Br # 22-0025). This project is proposed to reduce congestion, increase person throughput, provide multimodal access, promote ride sharing, improve mobility, and improve traffic operations. Also, provide innovative transportation management technologies, and promote opportunities and support for economic development.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|