Round Hill Pines Access Project

PROJECT WEBSITE: https://flh.fhwa.dot.gov/projects/nv/round-hill-pines/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/31/2022

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

Nevada State Seal

Nevada

Description:

FHWA-CFLHD, in cooperation with USDA Forest Service Lake Tahoe Basin Management Unit, Nevada DOT, and the Tahoe Regional Planning Agency, is proposing to improve safety for visitors entering and exiting the Round Hill Pines Resort from U.S. Highway 50. The project begins south of the existing entrance road into the resort and extends north along US Highway 50 for approximately 0.35 mile. The Project is located in Douglas County near Zephyr Cove, Nevada.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete