RM 2243

PROJECT WEBSITE: https://www.txdot.gov/projects/hearings-meetings/austin/archive/112918.html

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/26/2025

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed project would include phased reconstruction of Hero Way, and a large portion of RM 2243, to convert the existing facilities into the ultimate design, a controlled access facility with approximately 350–970-foot proposed ROW. The proposed project is approximately 7.7 miles in length and would involve approximately 102.7 acres of existing ROW, 374.34 acres of new ROW, and 26.3 acres of permanent easements.

The ultimate proposed project alignment runs (from west to east) along Hero Way for approximately 1.6 miles [between 183A and Ronald Reagan Boulevard (Blvd.)], continues for approximately 0.7 mile on new location alignment where it crosses existing RM 2243. The proposed alignment would run south of the existing RM 2243 facility for approximately 0.5 mile. The proposed project alignment connects with existing RM 2243 approximately 1.2 miles east of Ronald Reagan Blvd. The proposed project alignment then continues along the existing RM 2243 facility for approximately 5.0 miles, ending at SW Bypass.

The ultimate proposed main lanes include two 12-foot lanes in each direction with four-foot inside shoulders, and 10-foot outside shoulders. The east and west bound lanes would be separated by a concrete barrier. Frontages roads would consist of three 12-foot westbound lanes and three 12-foot eastbound lanes. The frontage roads would have a four-foot inside shoulder and two-foot curb and gutter on the outside. A 10-foot shared use path is also proposed along each frontage road. The main lanes and frontage roads would be separated by a 38-foot-wide open ditch consisting of a flat bottom and vegetative filter strips on the side slopes. There would be a five-foot inside grassy buffer between the frontage roads, shared use paths, and a varying 13-foot to 30-foot grassy buffer between the outside of the shared use paths and the proposed ROW line. Proposed drainage includes open ditches between the main lanes and frontage roads, and curb and gutter would be along the frontage roads with underground utilities. In the ultimate phase, grade separations are proposed at arterial cross-streets, and multi-level interchanges are proposed at 183A, Ronald Reagan Blvd., and SW Bypass. To see existing and proposed typical sections, refer to the final schematics under the “Project” heading in Documents with upload date 11/30/2022. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete