Riv 10 Blythe Pavement Rehab: mainline, shoulders, ramps (R134.0/R156.5)
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/27/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans) District 8 proposes to restore
and extend the life of the existing pavement on U.S. Interstate 10 (I-10) from Caltrans
post mile (PM) 134.00 to 156.50 within the city of Blythe and unincorporated portions
of Riverside County (Project). The Scope of the work includes; removal of existing
mainline AC pavement, removal of existing inside and outside shoulders, removal and
replacement of existing drainage inlets, all dikes, and over-side drains; removal and
replacement of all rumble strips, removal of guardrails and installation of Midwest
Guardrail System (MGS) with vegetation control; mill and overlay of all on and off
ramps with HMA- including those at the Wiley’s Well Rest Area; construction of CRCP
or JPCP and the associated base for traveled-way and all shoulders, including outside
shoulder backing on both roadbeds; widening of existing bridges, regrading of the
median and areas between the shoulders and the Caltrans ROW; construction of a
10-foot lane (cross-over lane) in the inside shoulder for traffic control; restriping,
construct reinforced concrete slope paving on all structures; and upgrading of the
existing ADA facilities at ramp termini.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|