Ritchie Creek Bridge Replacement Project for Fish Passage Improvement
PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-4/d4-popular-links/d4-environmenta…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/15/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans) proposes to replace the existing Ritchie Creek Bridge (Bridge No. 21-0057) with a new bridge at post mile (PM) 33.13, located on State Route 29 (SR 29) southeast of the city of Calistoga in Napa County. The new bridge dimensions would be similar to the existing bridge and would include a 12-foot travel lane and 8-foot shoulder in each direction.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|