Rehabilitation or Replacement of Cribari Bridge

PROJECT WEBSITE: http://www.ct.gov/dot/cwp/view.asp?a=3893&q=581086

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/31/2027

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

 The proposed project looks to rehabilitate or replace bridge no. 01349 (William F. Cribari Memorial Bridge, also known as Saguatuck Swing Bridge) which carries Route 136 over the Saugatuck River in the town of Westport, Connecticut. CTDOT released a Bridge Rehabilitation Study Report in June 2016. This planning-level study recommends that the bridge either undergo major rehabilitation or replacement due to the critical condition of the bridge's trusses. The trusses are in place for ornamental purposes only and carry no live load. Even so, failure to a primary truss member, if not properly maintained, could risk truss collapse and pose a safety hazard to vehicles and pedestrians. 
There is considerable public interest and concern with the project. Many members of the pubic value the existing
bridge's historic protections (bridge truss is listed on the NRHP), and there is concern that a rehab or replacement of the bridge would raise the vertical clearance and allow for semi-trailer trucks to cross, which is currently prohibited due to the low bridge height. Many members of the community prefer that truck traffic is minimal due to the vertical clearance restrictions.  FHWA/CTDOT intend to proceed with an Environmental Assessment, largely due to the high level of public controversy over Section 106 impacts. Alternatives developed through project scoping as of 5/2019 have estimated construction costs ranging from ~20-43 million.  Estimated total cost entered above is intend as an order of magnitude estimate based on this information.    
    
Project Location: (William F. Cribari Memorial Bridge), carrying Route 136 over the Saugatuck
River  

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete