Refugio Bridge Replacement

PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-5/district-5-current-projects/refu…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/02/2023

5 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

The California Department of Transportation (Caltrans) proposes to replace the existing Refugio Road Undercrossing Bridges (#51-0215R and #51-0215L) along State Route 101 near Refugio State Beach in Santa Barbara County between postmiles (PM) 36.1 and 37.1. This project was initiated after concrete core testing and an inspection of the structures by Caltrans Structure Maintenance and Investigations documented the presence of alkali-silica reactive aggregate in the concrete and recommended that both structures be completely replaced. A detailed Advanced Planning Study was prepared by Caltrans Structures Design and four proposed bridge design alternatives were identified for bridge replacement.

 

The proposed improvements would maintain the existing northbound and southbound traffic lanes, maintain the same bridge lengths, alignments, profiles, and provide safety improvements including upgraded bridge rails. Bridge supports such as abutments and bents vary by project alternative. Each new bridge is proposed to be six feet and four inches wider than the existing structures. In addition to replacing the bridges, rails on the smaller northbound on-ramp bridge would be upgraded. The concrete-grouted rock slope protection in Refugio Creek would be modified to provide adequate passage for anadromous fish. Permanent vegetation control would be installed under metal beam guardrail, and at the gore tip of the southbound Refugio Road off-ramp.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete