Point of the Mountain Transit Project
PROJECT WEBSITE: https://udotinput.utah.gov/pointtransit
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/19/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
The Utah Transit Authority (UTA) in collaboration with the Utah Department of Transportation (UDOT) propose to construct the Point of the Mountain (POM) Transit Project. The POM Transit Project is a proposed 10‑mile‑long, high-capacity transit line to be constructed between Draper and Lehi, UT with up to 11 proposed stations, and supporting facilities. Three modes are being considered for the proposed transit line including bus rapid transit (BRT), light rail transit (LRT), and multiple-unit rail (XMU). UTA and UDOT plan to construct the transit line in partnership with the Wasatch Front Regional Council, Mountainland Association of Governments, Utah County, Salt Lake County, and the cities of Bluffdale, Draper, Lehi, Sandy, and South Jordan, UT.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|