Pelham Bay Bridge Replacement Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/05/2028

4 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Description:

Amtrak proposes to replace the existing two-track moveable bridge, constructed in 1907.The Project would result in the replacement of the existing Pelham Bay Bridge, inclusive of the movable bascule span and the north and south approach structures, with a new two-track bridge across the Hutchinson River while maintaining train and marine traffic. The existing tracks would be realigned and the existing infrastructure, such as the catenary structures and other power and signal equipment would be modified to support construction of the new bridge. The replacement bridge would be located adjacent to the existing bridge and would not result in increased capacity over the bridge or an increase in the number of trains travelling over the bridge.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete