Old Highway 41 Highway Road Widening and Operational Improvements

PROJECT WEBSITE: https://old-41-hwy-widening-0016410-gdot.hub.arcgis.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/01/2027

2 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The project is a roadway widening and realignment project located in Cobb County, Georgia. The proposed project would widen and realign the existing two-lane roadway between Kennesaw Avenue and Stilesboro Road. The total project length is approximately 0.71 miles. The roadway will be realigned to move the roadway to the north limit of the Kennesaw Mountain National Battlefield’s (KEMO) property. At the western end of the project, the Old 41 Highway/Stilesboro Road intersection will be reconstructed as a single lane roundabout with a westbound through bypass lane and a dedicated northbound to eastbound right turn lane. A second roundabout is proposed at Kennesaw Avenue. This roundabout will also provide a dedicated westbound through bypass lane. Between the proposed roundabouts, the project will widen the road to include two lanes in each direction, a raised median, and curb and gutter. The project also proposes the construction of a path tunnel beneath the south leg of the Old 41 Highway/Stilesboro Road intersection to allow park users to access the park’s amenities from the overflow parking lot without crossing Stilesboro Road.
 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete