Old Conroe Road Widening and Extension

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/09/2025

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed improvements would include widening Sgt. Ed Holcomb Boulevard and Old Conroe Road within the project limits to four 12-foot-wide travel lanes (two in each direction) with the addition of a 14-wide center turn lane or a 16-foot-wide grassy median, a 10-foot-wide shared use path on the east side, and curb-and-gutter drainage. Intermittent 6-foot-wide sidewalks would also be constructed on the west side of the facility in three locations: Loop 336 to Riverway Drive, Foster’s Ridge Parkway to Thunder Basin Parkway, and north of Landing Drive to FM 1488. The facility would be extended (connected) with construction of a new bridge over the West Fork San Jacinto River and Lake Creek. The bridge would consist of four 12-foot-wide travel lanes separated by a concrete barrier, with 10-foot-wide outside shoulders and a 14-foot-wide shared use path on the east side.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete