NYS Route 5 (Buffalo Skyway) Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The New York State Department of Transportation, in cooperation with the FHWA, will prepare an EIS in accordance with the National Environmental Policy Act for the New York State (NYS) Route 5 (Buffalo Skyway) Project, located in Erie County, New York.  The Buffalo Skyway/NYS Route 5 interchanges, approaches and infrastructure, extending 3.5 miles from Tifft Street to Church Street, occupy approximately 45 acres of land along the Buffalo waterfront. Over the past few decades, this area has undergone a substantial change in land use with a focus on recreational, mixed-use, and waterfront development. The purpose of the Project is to realign the existing transportation network to support existing and planned recreational, mixed-use, and waterfront development in the Buffalo Outer Harbor and Inner Harbor areas. The Project will also address the safety, operational, and capacity deficiencies of the highway connections that serve economic development areas and local communities within South Buffalo.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete