Northern Relief Route

PROJECT WEBSITE: https://www.txdot.gov/projects/projects-studies/san-angelo/san-angelo-north-rel…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/31/2027

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed project would extend for approximately 11 miles on new location between US 87 and US 67 just north of San Angelo, Texas. In addition, work would be conducted on approximately two miles of US 87, 0.15 mile of Grape Creek Road, 0.26 mile of Rust Road, 0.10 mile of SH 208, 0.10 of Red Creek Road, 1.14 miles of US 277, and 0.92 mile of US 67 to facilitate intersections or interchanges with each of these cross streets. Approximately 186.3 acres of existing right of way (ROW) would be incorporated from these and other cross streets. The proposed project’s ROW would generally be 500 feet wide, and up to approximately 112 feet of additional ROW is proposed along a portion of US 67, totaling approximately 575 acres of proposed ROW. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete