Naval Station Norfolk Transit Corridor Phase 1
PROJECT WEBSITE: https://www.navalstationnorfolktransit.com/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
							ENVIRONMENTAL REVIEW AND PERMITTING STATUS
							PAUSED
						
																																				ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
															SUBJECT TO CHANGE
													
							ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
							COMPLETED
						
								SECTOR
								Surface Transportation
							
							CATEGORY
																						
								Project Category
              DOT Projects
																				
 
																	
								LEAD AGENCY
																	Department of Transportation, Federal Transit Administration
															
Description:
The Hampton Roads Transit proposes to extend the Tide Light Rail Transit from its eastern terminus at the Newtown Road Station to the Military Circle Mall redevelopment site in Norfolk, Virginia. The project was identified as Phase 1 of the Naval Station Norfolk Transit Corridor Project study which evaluated options to provide high-capacity transit on the east side of the City of Norfolk between the existing Tide Light Rail system and Naval Station Norfolk.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete | 
|---|