Muir Woods Road Improvement Project

PROJECT WEBSITE: https://parkplanning.nps.gov/projectHome.cfm?projectID=68334

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/01/2026

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The Federal Highway Administration (FHWA), Central Federal Lands Highway Division (CFLHD), in cooperation with  Marin County, the National Park Service (NPS), and California State Parks are proposing to improve access along a segment of Muir Woods Road. The proposed project would improve improve 2.42 miles of Muir Woods Road (Route County Road 107) in Marin County. 

The purpose of the proposed action is to restrore the structural integrity of the road to improve access to state and federal lands, to enhance safety for all users, correct road-related drainage problems, reduce water quality impacts to Redwood Creek, and reduce on-going road maintenance requirements. The purpose of the bridge project is to replace the Muir Woods Road Bridge over Redwood Creek, which was constructed in 1946 and does not meet current bridge standards.  

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete