Mid-States Corridor Section 2 Tier 2

PROJECT WEBSITE: https://midstatescorridor.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/30/2027

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The Mid-States Corridor Section 2 project proposes to construct a new roadway facility located on the east side of the cities of Huntingburg and Jasper in Dubois County, Indiana from I-64 at Dale to SR 56 at Haysville. The project is part of a Tiered National Environment Policy Act (NEPA) process. The Tier 1 Record of Decision (ROD) for the Mid-States Corridor project was published September 15, 2023 and selected the corridor for the Tier 2 NEPA studies. Four Sections of Independent Utility (SIU) for Tier 2 NEPA studies were identified. SIU 2 (Section 2), which extends from I-64 at Dale to SR 56 at Haysville, is the focus of this project. The primary purposes of the project are to (1) Improve regional connectivity in Dubois County and Southern Indiana; (2) Improve highway connections to existing multimodal locations from Southern Indiana; and (3) Complete Section 2 of the Mid-States Corridor Project between I-64 at Dale and SR 56 at Haysville. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete