MAD-99-NORTH MADERA 99 6-Lane

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/03/2028

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

The project would widen SR 99 from a 4-lane freeway to a 6-lane freeway between Post Mile (PM) 15.1 and PM 19.9. The project would remove and replace the existing pavement with 0.25 foot of Hot Mix Asphalt (HMA) and 1.10 feet of Continuously Reinforced Concrete Pavement (CRCP). The two new lanes
would receive the same proposed treatment. Also, the project would install inside and outside shoulders rumble strips along the SR 99 northbound and southbound lanes. The project would also remove and replace three culverts at PM 16.91, PM 17.1 8 and PM 19.04. The project would remove and replace the Berenda Creek bridge at PM Rl 6.10 and the Dry Creek bridge at PM 17 .86.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete