Loop 88 (FM 1585)
PROJECT WEBSITE: Public Meeting - Lubbock Outer Route from US 87 to US 62/82
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/27/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Texas
Description:
The proposed project would upgrade and widen FM 1585 by converting the existing two 12-foot lanes and two 10-foot shoulders roadway to a four lane divided freeway with frontage roads and ramps. Interchanges will be developed at cross streets. Additionally, interchanges and direct connectors will be constructed at US 87 and US 62/82. |
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|