Lake Chelan Airport Runway Shift

PROJECT WEBSITE: https://cityofchelan.us/DocumentCenter/View/843/Lake-Chelan-Airport-Presentatio…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/16/2026

0 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

The proposed action would shift Runway 2/20 and extend the runway approximately 897 feet in length. Other projects associated with the proposed action:

  • Acquisition of about 116 acres in fee or easement and removal of orchard trees to allow for development
  • Relocation of existing runway and taxiways
  • Relocation of Howard Flats Road
  • Taxilane construction
  • Fuel system relocation
  • Relocation of existing hangars
  • Modifications to existing irrigation district and private landowner irrigation systems on properties to be acquired for aircraft development
  • Automated Weather Observing System installation

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete