LaGuardia Airport Access Improvement Project, Environmental Impact Statement
PROJECT WEBSITE: LGA Access EIS
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/20/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
The Port Authority of New York and New Jersey (Port Authority) proposes to construct an elevated automated people mover (APM) that would provide direct access between LaGuardia Airport (LGA) and two existing transit stations at Mets-Willets Point. The Port Authority’s preferred alternative would include two on-airport stations with a terminus station at Willets Point providing connections to the Mets-Willets Point stations of the Long Island Rail Road and the New York City Transit No. 7 subway line. The purpose of the Port Authority’s proposed project is to provide air passengers and employees with a time-certain option for access to LGA and permit the Port Authority to provide adequate employee parking for the geographically constrained airport.
September 2023 Update: The FAA is withdrawing the July 2021 ROD for the Project. The Port Authority of New York and New Jersey has notified the FAA of its intent to terminate the Project and pursue alternative access improvements to LGA. Accordingly, the components identified in the LGA Access Improvement Project ROD are no longer needed at this time.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|