King of Prussia - Norristown Extension
PROJECT WEBSITE: King of Prussia Rail Project Website
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/08/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
The Southeastern Pennsylvania Transportation Authority (SEPTA) initiated the King of Prussia Rail Project to evaluate an extension of the Norristown High Speed Line (NHSL) to the King of Prussia area. The NHSL currently provides service between the 69th Street Transportation Center and Norristown Transportation Center, serving the Main Line area in Delaware and Montgomery Counties, and connecting to Center City Philadelphia. While the transit system is expansive, a rail connection to the King of Prussia area is missing. Travel to King of Prussia currently occurs by bus or vehicle. Frequent traffic congestion can cause unreliable travel times, hinder transit ridership, and limit growth. The King of Prussia Rail Project will evaluate various alternatives for a new rail connection between the existing NHSL and destinations in King of Prussia.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|