Jefferson Highway Rail Crossing Relocation

PROJECT WEBSITE: Jefferson Highway Rail Crossing Relocation Study

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/01/2032

2 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

No icon

Louisiana

Description:

The project plans to consolidate and grade-separate two at-grade highway-rail crossings of U.S. 90 (Jefferson Highway) between Harding Street in Jefferson Parish and Mistletoe Street in Orleans Parish, Louisiana.  The project is evaluating realigning the railroad tracks north of Jefferson Highway to combining two crossings into a single dual-track crossing at either the Canadian National/New Orleans Public Belt Railroad (CN/NOPB) or Canadian Pacific and Kansas City Southern (CPKC) crossing location, with the crossing either remaining at-grade or constructing a grade separated roadway overpass including frontage roads to connect to the local roadway network.   The two existing at-grade highway-rail crossings are Jefferson Highway (US 90), a Canadian National/New Orleans Public Belt Railroad crossing and a CPKC crossing between Brooklyn Avenue and Monticello Avenue are located less than 700 feet apart. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete