IMPROVE FREEWAY ACCESS & ARTERIAL CONNECTION TO I-605
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/03/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans) District 12, in cooperation with the
Orange County Transportation Authority (OCTA), proposes to improve the local interchange at
Interstate 605 (I-605) and Katella Avenue. The project is located within the limits of the City of
Los Alamitos, in Orange County, on I-605 from PM 1.1 to 1.6. The I-605/Katella Avenue
Interchange is located approximately 1.3 miles north of the I-405/I-605 junction, and
approximately 5 miles south of State Route 91 (SR-91). Within the vicinity of the proposed
project, I-605 has four general purpose lanes in each direction and one high occupancy vehicle
(HOV) lane in each direction. From the I-405 interchange to Katella Avenue, there is an auxiliary
lane in each direction and a sound barrier along the northbound right shoulder. The purpose of
the proposed project is to improve interchange traffic operations, and improve pedestrian and
bicycle facilities within the project limits.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|