IH 14 Extension- US 190 to I-35

PROJECT WEBSITE: I-14 Extension: I-35 from Loop 121 in Belton to Loop 363/US 190/SH 36 in Temple

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/07/2028

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The I-35 improvements in Bell County stretch seven miles from south of Loop 121 in Belton to Loop 363/US 190/SH 36 in Temple. The proposed improvements include: improving the I-14/US 190/I-35 system interchanges; widening I-35 in Segment 1; and improving overall safety, connectivity and mobility. Currently, the existing typical section along this corridor of I-35 includes three general-purpose lanes and two frontage road lanes in each direction; the proposed typical section would include, in each direction, an additional general-purpose lane for a total of four general-purpose lanes, three express lanes, two to three frontage road lanes and a shared-use path. Segment 1 is part of a larger project that will extend I-14 from its current terminus in Belton to BU 190 in Rogers, comprising a total of three segments.

The proposed project may acquire new right-of-way (ROW). Potential new ROW would be used to accommodate additional lane capacity related to the I-35 improvements. TxDOT anticipates making a de minimis determination for this use under Section 4(f) of the Department of Transportation Act of 1966. Public comment on the effects of the proposed project on the activities, features, or attributes of Liberty Park may be submitted as described below.

The proposed project may involve construction in wetlands.

The proposed project may involve an action in a floodplain.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete