I-95 Access Improvements
PROJECT WEBSITE: http://mdta.maryland.gov/Capital_Projects/I-95_Access_Study/Home.html
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The I-95 Access Improvements Project would include improvements to southbound and northbound ramps on I-95, McComas Street, Hanover Street, Key Highway, and the CSX Railroad Bridge,
as well as modification of the CSX side-track that serves the Port Covington site.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|