I-84 Hartford Project
PROJECT WEBSITE: I-84 Hartford Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
Connecticut Department of Transportation (CTDOT) is investigating the need to rehabilitate, reconstruct, or replace Interstate 84 (I-84) through Hartford: The I-84 Hartford Project. The I-84 Hartford Project corridor is approximately three miles in length and encompasses the interchanges and elevated bridge sections of the highway from as far west as Hamilton Street to the I-91 Interchange on the east.
The purpose of the I-84 Hartford Project is to address structural deficiencies, improve traffic operations and safety, and improve mobility on the I-84 mainline and its interchanges between Flatbrush Avenue and I-91 in Hartford. A high-level planning study was completed in 2010. Scoping started in December 2014 under the assumption that the class of action would be an EA. The Section 6002 Agency Coordination Process was followed. After initial studies of anticipated resource impacts, the FHWA and the CTDOT determined it appropriate to develop an EIS. The NOI to Prepare an EIS was published on 9/20/16 (81 FR 67421). Project is now undergoing environmental studies and alternatives analysis leading into the DEIS. Planned future milestones: DEIS 3/8/19; FEIS 4/8/20; ROD 6/17/20.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|