I-81 Viaduct
PROJECT WEBSITE: I-81 Viaduct
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/31/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
New Road Construction
The New York State Department of Transportation (NYSDOT) is proposing to address the existing structural, geometric, and operational deficiencies of Interstate 81 (I-81) from approximately Colvin Street to Hiawatha Boulevard (the “I-81 Viaduct Project”) in the City of Syracuse, Onondaga County, New York. NYSDOT is also investigating modifications along Interstate 690 (I-690) approximately between its interchange at West Street and Lodi Street and potential improvements on Interstate 481 (I-481) from its southern to northern termini. The project limits have been defined to include an approximately 3.75-mile section of I-81 from Colvin Street to Hiawatha Boulevard and the 2.5-mile section of I-690 from approximately the West Street interchange (which extends to Leavenworth Street) to Lodi Street. It should be noted that the project limits are dynamic and may be revised as options for the I-81 Viaduct Project are explored.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|