I-80/Ashby Avenue (SR-13) Interchange Improvements

PROJECT WEBSITE: I-80/Ashby Avenue (SR-13) Interchange Improvements

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/31/2022

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

The Alameda County Transportation Commission (Alameda CTC), in cooperation with the California Department of Transportation (Caltrans) and the cities of Berkeley and Emeryville, proposes to reconstruct the I-80/ Ashby Avenue interchange to improve accessibility, safety, traffic flow, and bicycle and pedestrian facilities. These improvements are intended to provide traffic congestion relief and enhanced mobility at this critical access point and important intersection of regional transportation routes. The project will also provide multimodal transport options, while improving community connectedness, including connectivity to the existing Bay Trail. This project was approved by Alameda County voters in 2014 under Measure BB and represents a direct investment in regional infrastructure and economic development. It will provide a direct connection between westbound Interstate 80 (I-80) and Emeryville by way of Shellmound Street.

Improvements will include:

  • A new bridge to replace existing bridges
  • A new interchange form with connections to Shellmound Street and Frontage Road
  • Provision of bicycle and pedestrian access over the I-80 freeway at the Ashby Avenue interchange

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete