I-80 17M Reconstruction (1306-EA)
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/30/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The Pennsylvania Department of Transportation (PennDOT), in cooperation with Federal Highway Administration (FHWA), is moving forward with the environmental studies and preliminary design for the Interstate 80 (I-80) Reconstruction Project (SR 0080 Section 17M) in eastern Monroe County, Pennsylvania. The I-80 Reconstruction Project includes 3.5 miles of full roadway reconstruction, widening, and interchange reconfiguration. The roadway in this region serves as a major carrier of local and regional commuter traffic; local, regional, and national freight; and local and regional tourism. The project corridor serves as a gateway to the Pocono resort areas as well as the Delaware Water Gap National Recreational Area. Originally constructed in the 1960s, the roadway has suffered significant deterioration in recent years, no longer meets multiple design criteria and carries significantly higher traffic volumes than originally designed to carry.
The project corridor passes through three municipalities within Monroe County: Stroud Township to the west, the Borough of Stroudsburg and the Borough of East Stroudsburg to the east. The project limits run from just west of the 303 interchange to east of exit 307 and the Brodhead Creek bridge in East Stroudsburg. The project area includes the 303, 304, 305, 306 and 307 interchanges.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|