USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

I-75 Commercial Vehicle Lanes

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/01/2028

1 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The project proposes the addition of two commercial vehicle lanes (CVLs) in the northbound (NB) direction along the I-75 corridor from Interstate 475 (I-475) north of Macon beginning at the I-75/I-475 interchange near the Monroe/Bibb County line to the I-75/State Route 155 (SR 155) near McDonough in Henry County and includes the addition of an auxiliary lane beginning south of SR 155 and between SR 155 and SR 20. The total length of the proposed Project is approximately 41 center-line miles and approximately 4.4 miles associated with cross-roads and interchanges. The CVL project is one project in the Georgia Department of Transportation (Georgia DOT) Major Mobility Investment Program (MMIP), which is being implemented to improve trip time reliability along key freight and passenger corridors.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete