I-69 Tier 2 Section 6 SR 39 to I-465
PROJECT WEBSITE: I-69 - Evansville to Indianapolis; Section 6-Martinsville to Indianapolis
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/09/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
New construction
Tier 2 Environmental Impact Statement (EIS) for the proposed Section 6 of I–69 is located in Morgan, Johnson and Marion Counties, Indiana, of the Evansville-to-Indianapolis Interstate 69 (I–69) highway. Section 6 begins south of the SR 39 / SR 37 interchange in Martinsville, and continues northward to I-465 in Indianapolis. This section is approximately 26 miles long.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|