I-69 Evansville, IN - Henderson, KY

PROJECT WEBSITE: I-69 OHIO RIVER CROSSING

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/01/2027

3 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

Department of War Seal

Department of War, US Army Corps of Engineers - Regulatory

Department of Homeland Security

Department of Homeland Security, US Coast Guard

Department of the Interior

Department of the Interior, Fish and Wildlife Service

No icon

Indiana

Description:

This was originally a KY lead project named Future I-69 Bridge over the Ohio River Between Henderson and Evansville near US-41 Bridges (2-1088).

Purpose of the project will be to develop a financially feasible solution to the project’s identified needs. At this time, the anticipated primary purpose of this project will be to:
• Provide cross-river system linkage and connectivity between I-69 in Indiana and I-69 in Kentucky that is compatible
with the National I-69 Corridor.
• Develop a solution to address long-term cross-river mobility.
• Provide a cross-river connection that reduces traffic congestion and delay.
• Improve safety for cross-river traffic.

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete