I-680 Northbound Express Lane Completion Project
PROJECT WEBSITE: https://680xpresslanesproject.com/home/home/#project-limits
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/08/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
The California Department of Transportation (Caltrans) and the Contra Costa Transportation Authority (CCTA)proposes to construct a northbound express lane from Livorna Road to State Route 242 (SR-242). It would also convert the existing northbound high-occupancy vehicle (HOV) lane that runs from SR-242 to the Benicia-Martinez Bridge Toll Plaza, to an express lane.
As a major north-south freeway, I-680 is a heavily traveled corridor that connects the southern San Francisco Bay Area with Interstate 80 (I-80) and passes through Santa Clara, Alameda, Contra Costa and Solano counties. Within Contra Costa County, travelers experience congestion, traffic bottlenecks within the corridor, and increased travel times. To improve system continuity, congestion relief and operations, the project—part of CCTA’s INNOVATE 680 program—proposes to construct a northbound express lane from Livorna Road to State Route 242 (SR-242). It would also convert the existing northbound high-occupancy vehicle (HOV) lane that runs from SR-242 to the Benicia-Martinez Bridge Toll Plaza, to an express lane. The goal of the project is to complete the I-680 express lane network through Contra Costa County to increase travel speeds for those choosing to use the express lane.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|