I-405 Sepulveda Pass ExpressLanes Project
PROJECT WEBSITE: https://www.metro.net/projects/i-405-expresslanes-project/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/18/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans), in cooperation with the LA County Metropolitan Transportation Agency Authority (Metro), proposes to improve traffic conditions on Interstate 405 (I-405) between I-10 and US-101 in Los Angeles County. The project proposes to reduce congestion, encourage carpooling and transit, improve trip reliability, reduce degradation of the carpool and general purpose lanes, increase person throughput, and apply technology to help manage traffic. The range of improvements may include, but not be limited to, converting existing high-occupancy vehicle (HOV) lane to ExpressLanes or adding an additional ExpressLane in each direction and converting existing HOV lanes to ExpressLanes. The study area includes the Cities of Los Angeles, Culver City, and Santa Monica, as well as unincorporated Los Angeles County.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|