I-39/90/94 Corridor Study-US 12/18 Madison -US 12/WIS 16 Wisconsin Dells (Dane Columbia Sauk Juneau)
PROJECT WEBSITE: https://wisconsindot.gov/Pages/projects/by-region/sw/399094/default.aspx
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/01/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Environmental Protection Agency
Description:
The Interstate 39/90/94 Corridor Study will assess how best to address existing and future traffic demands, safety issues, aging and outdated infrastructure and corridor resiliency in Dane, Columbia, Sauk and Juneau counties. The project will consider new interchanges in Madison, WI at Hoepker Road/I-39/90/94 and Milwaukee Street/I-94. The project will also include I-39 from the I-39 and I-90/94 Split Interchange to Levee Road
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|