I-280/Winchester Boulevard Interchange Improvements
PROJECT WEBSITE: https://www.vta.org/projects/i-280winchester-boulevard-interchange-improvements
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/04/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans), in cooperation with the Santa Clara Valley Transportation Authority (VTA) and the City of San Jose, proposes to construct improvements in the vicinity of the Interstate 280 (I-280)/Winchester Boulevard Interchange.
The purpose of the project is to:
- Improve traffic operations and reduce congestion on the local roadways in the project area.
- Provide new access from northbound I-280 to the project area.
- Improve bicycle and pedestrian access and transit connectivity in the project area.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|