Highway 5 Improvements Project

PROJECT WEBSITE: https://www.carvercountymn.gov/departments/public-works/projects-studies/highwa…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/13/2026

8 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

No icon

States

Description:

The Highway 5 Improvements Project is in the Cities of Chanhassen and Victoria in Carver County. The western project terminus is at Commercial Avenue on the east side of downtown Victoria and the eastern terminus is the Highway 5/Highway 41 intersection in the city of Chanhassen. The total length of the project is approximately 3.25 miles.  The purpose of the Highway 5 Improvements Project is to improve vehicle mobility and safety for all users, including passenger vehicles and freight haulers, while also ensuring reasonable access to private property and businesses and enhancing active transportation facilities to benefit walkability and bikeability within the study area.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete