FM 552 Widening (SH 205 - SH 66)
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/23/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
The existing facility is a rural undivided roadway with two 11-foot wide lanes (one in each direction) with 3-foot shoulders within a an existing variable right-of-way (ROW) of 80- to- 130 feet.
The proposed facility would consist of an urban median separated roadway with four travel lanes (two in each direction). The two inside travel lanes would be 12-ft wide and the outside travel lanes would be 14-ft wide to accommodate shared-use of bicycles and vehicles. The proposed facility would include a raised median from
SH 205 to John King Boulevard and from Dismore Lane to SH 66; and a 20-foot flush median between John King Boulevard and Dismore Lane. The project includes 6- or 10-foot wide sidewalks along the road within an approximate variable ROW of 124- to 136 feet.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|