FM 548 Widening

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/03/2019

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The Texas Department of Transportation (TxDOT) and Kaufman County propose improvements to the existing Farm-to-Market Road (FM) 548 from north of U.S. Highway (US) 80 to State Highway (SH) 205 in Kaufman and Rockwall Counties, Texas. The total project length is approximately 7.8 miles. There are two segments to the proposed project. Segment 1 would involve the expansion from a two-lane rural roadway to a six-lane divided urban minor arterial from US 80 to Windmill Farms Boulevard. Segment 2 would involve the expansion from a two-lane rural roadway to a four-lane divided urban arterial (six-lane divided ultimate) from Windmill Farms Boulevard to SH 205.  

The proposed alignment generally matches the existing alignment. The existing horizontal curve south of University Drive would be realigned. The proposed project includes the replacement of an existing bridge structure over Big Brushy Creek and replacement of five existing bridge class culverts and four non-bridge-class culverts. The proposed typical section includes closed drainage (curb-and gutter and storm sewer) for FM 548 for the entire limits of the project.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete