Enfield Railroad Station Hartford Line Rail Program
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/09/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Railroad Administration
Other Agencies with Actions or Authorizations:
Connecticut
Department of the Interior, Fish and Wildlife Service
Department of Commerce, National Oceanic and Atmospheric Administration
Description:
The proposed project would conduct environmental review, preliminary engineering, final design, and construction of a new Enfield Station to accommodate increased service as part of the New Haven-Hartford-Springfield Rail Program and improve under bridge clearance. Specific improvements will include, a 500-ft level boarding platform, a utility building with waiting area, and station parking. Track and signal work are needed to support the platform, and the clearance will be improved by raising the bridge and lowering the road. Benefits include increased clearance under a bridge making it safer for pedestrians, cars, and trains, and as well as proposed station improvements such as security cameras, ADA compliant infrastructure and electric vehicle charging infrastructure.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|