USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Eastside Transit Corridor Phase 2 Project

PROJECT WEBSITE: https://www.metro.net/projects/eastside_phase2/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/22/2026

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The Los Angeles County Metropolitan Transportation Authority (LACMTA) proposes to construct the Eastside Transit Corridor Phase 2 Project (Project).  The Project’s Locally Preferred Alternative (also known as the Initial Operating Segment [IOS] to Greenwood) is an approximately 4.7-mile light rail line extending from the current E Line terminus in East Los Angeles to Greenwood Avenue and Washington Boulevard in the City of Montebello. The Project is located in eastern Los Angeles County, California, and would run through the unincorporated Los Angeles County community of East Los Angeles and the cities of Commerce and Montebello. The proposed light rail extension will feature a relocated station at Atlantic/Pomona in East Los Angeles and three new stations, which include one new station at the Atlantic/Whittier intersection, one new station in Commerce Citadel, and one new station at the Greenwood/Washington intersection in Montebello.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete