Dallas-Fort Worth High-Speed Rail Service
PROJECT WEBSITE: http://www.nctcog.org/dfw-hstcs
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
The North Central Texas Council of Governments (NCTCOG), in cooperation with the Federal Transit Administration (FTA), is conducting engineering and environmental studies for a new, high-speed passenger rail service and associated infrastructure between downtown Dallas and downtown Fort Worth, approximately 31 miles. The proposed alignment generally follows Interstate Highway 30. The proposed rail service would traverse Dallas and Tarrant counties and the cities of Fort Worth, Arlington, Grand Prairie, and Dallas.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|