Dallas Central Business District Second Light Rail Alignment (D2)
PROJECT WEBSITE: Dallas Central Business District (CBD) Second Light Rail Alignment Project Webs…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/29/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
The Downtown Dallas Transit Project is studying the options for a second Dallas Area Rapid Transit (DART) light rail alignment through downtown. A Draft EIS was circulated in March 2010. The proposed D2 Project consists of approximately 2.4 miles light rail alignment with up to five new light rail stations in the Central Business District of Dallas. A Locally Preferred Alternative and design options are being studied. The D2 Project will increase system capacity, provide operational flexibility, and serve new markets.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|