Congestion Pricing- VPPP
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/23/2023
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The Triborough Bridge and Tunnel Authority (TBTA)—an affiliate of the Metropolitan Transportation
Authority (MTA)—the New York State Department of Transportation (NYSDOT), and the New York City
Department of Transportation (NYCDOT) are the Project Sponsors for the Manhattan Central Business
District (CBD) Tolling Program (the CBD Tolling Program or the Project), in New York, New York. In
cooperation with the Federal Highway Administration (FHWA) as the lead Federal agency, the Project
Sponsors are preparing an Environmental Assessment (EA) in accordance with the National Environmental
Policy Act (NEPA).1 The EA will analyze the potential environmental effects of implementing the CBD Tolling
Program.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|