Conflans Rd Extension

PROJECT WEBSITE: Keep It Moving Dallas

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/03/2022

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Other Agencies with Actions or Authorizations:

Department of War Seal

Department of War, US Army Corps of Engineers - Regulatory

Description:

Currently, existing Conflans Road is a major collector in the southwest portion of Irving, which ends at SH 161. The proposed improvements for this project would extend existing Conflans Road approximately 0.8-mile west of SH 161, on a new location roadway and bridge structure, to connect to Valley View Lane at F.A.A. Boulevard. The proposed bridge structure would cross over a tributary of Bear Creek. The new location roadway and bridge structure would consist of one 12-foot wide inside travel lane and one 14-foot wide outside shared-use lane (for bicycle accommodation), curb and gutter, and one 12-foot shared use path along the outer lanes of the roadway on the eastbound direction. The proposed shared-use path would meet ADA design criteria. Approximately 16 acres of new right of way and 6.5 acres of temporary easements would be acquired for construction of the project.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete