COA Braker Lane Extension

PROJECT WEBSITE: https://www.txdot.gov/projects/hearings-meetings/austin/archive/east-braker-lan…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/14/2023

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Other Agencies with Actions or Authorizations:

Department of Transportation

Department of Transportation

Description:

New four-lane arterial roadway is divided by medians with a median break at Taebaek Drive. Center-turn lanes for vehicles turning onto Taebaek Drive or Samsung Boulevard from Braker Lane. Sidewalks on both sides of the street along the project limits. Pedestrian crossing at Taebaek Drive to provide space for people walking, biking, and rolling to cross safely. Installation of a protected bicycle lane on the north side and an off-street bicycle lane on the south side. Extension of Taebaek Drive to connect to new East Braker Lane roadway. Curb, gutter and drainage improvements. Detention pond for runoff and water quality enhancements.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete