City of Douglas International Port of Entry (POE) Connector Road Study
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/21/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Arizona
Description:
The City of Douglas International POE Connector Road Study (Connector Road Study), proposes to connect the second International POE to the State Highway System.
The project is located in the City of Douglas and unincorporated Cochise County. The proposed International POE is approximately 4.5 miles west of the City of Douglas limits and is the designated location for construction of a proposed commercial port of entry.
The purpose of this project is to provide connectivity from the proposed second international port-of-entry (IPOE) near Douglas to the state highway system.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|