Chicago O'Hare International Airport, Terminal Area Plan and Air Traffic Procedures
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/17/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
O’Hare Airport proposes to modernize to provide updated facilities, retain operational efficiency for existing and future demand, avoid additional delay, and consolidate facilities. The City completed a draft ALP update to depict the proposed Terminal Area Plan (TAP), Capital Improvement Projects, and hotel developments. The major projects involves consolidating reconstructing Terminal 2 into a global terminal. FAA proposes to permanently implement 2.5-degree offset (angled) air traffic approach procedures for Runway 10R/28L that were temporarily approved in the 2015 Written Re-Evaluation of the O’Hare Modernization Program Environmental Impact Statement (OMP EIS).
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|